People on American Canyon’s east side who want Newell Drive extended will have to wait longer to learn whether a developer has to build the next piece of it. On Nov. 17 the City Council put off a decision on letting the builder of the 216-home Promontory subdivision drop its duty to build that stretch.
The vote to put off the hearing was 5-0. No new date was set. Several council members said they wanted Sindy Biederman, the top vote-getter in the Nov. 3 council race, to have a say. Vice Mayor Mark Joseph, at his last meeting, said he was happy to let his replacement make that call.
What the developer wants
Promontory is 216 single-family homes, with 54 junior accessory units built into them, in the Watson Ranch area on the city’s east side. The council approved it in 2023, with a condition that the developer, 330 Land Co., build Newell Drive Segment 1, from where the road now ends near Mallen Way to Rio Del Mar.
The council approved the final maps in December 2025. In March the developer filed a protest under the state Mitigation Fee Act, according to the staff report. It argued the city was making it build and give up more than the law allows, and the city disagreed. In June the two sides reached a settlement: the developer drops its claims if the council approves a revised project. The maps still haven’t been recorded.
The revised project drops Segment 1, two planned roundabouts and a storm basin. It narrows the part of Newell the developer would still build, along the edge of its own land, to two lanes and a 12-foot trail, ending 120 feet short of the property line. In place of Segment 1, the developer would build a 17-foot paved road closed to public traffic, for emergency vehicles, that people could walk as a trail. The fire district had warned that without it, the subdivision would have one way in.
Drivers can reach the subdivision by Mallen Way, which runs parallel to Segment 1 and serves the same function, the developer’s traffic analysis shows, according to the proposed resolution. The strip of land for Segment 1 has been dedicated to the city and will stay in place for the road to be built later, the resolution says.
Why the road matters
The city has described a longer Newell Drive as “a parallel roadway east of SR 29 to relieve chronic peak-period traffic congestion.” If an emergency blocks the highway, it would also give drivers a way out, the city said in an environmental filing for a nearby annexation.
Council Member Brando Cruz, who said he lives on the east side, said residents there have talked about Newell “for 25 years.” “We just want to get it built,” he said.
Council Member David Oro said he walks Mallen Way every day. If Newell traffic is routed there, he said, “that stop sign is going to be a hot mess.”
An online caller who said he drives through Mallen Way and Rio Del Mar most days called the three-way stop “a big bottleneck” and wanted to see the June settlement. It isn’t among the 11 attachments to the staff report. Another speaker, Robert Cole, asked, “why is American Canyon caving on this now instead of just holding to what they believe was right?”
Two neighboring landowners also wrote in. American Canyon 1 LLC, which owns most of Watson Ranch, said it didn’t oppose the project but had unanswered concerns, City Attorney Matthew Summers told the council. Owners of the 280-acre Hess-Laird property to the north raised objections under state environmental law and the city’s plans. Both asked the council to wait.
The $15 million question
Steve Riley of 330 Land Co. told the council the company never refused to build the roads. It objected to paying for more than its share, he said. Promontory holds about 13% of the land in the Watson Ranch plan, he said, and the off-site work first required of it came to about $15 million, which he put at about $75,000 a house. Spread across 216 homes, $15 million comes to about $69,000 each.
“We would be very happy tonight to even come to an agreement to work on a way to build Newell Drive segment one,” Riley said, “so long as we were going to get reimbursed either via fee credits or some other mechanism.”
Joseph, who called himself a longtime champion of the Newell extension, said the road “started from a very grandiose 120 foot wide four lane kind of a boulevard” and has “slowly but surely shrunk down.” He asked that the developer post a bond or pay for the 120-foot gap so the road can be finished “not necessarily at the taxpayers expense.”
What happens next
Summers told the council the developer can still build the project approved in 2023, with Segment 1, whatever the council decides. The city will publish a new notice when the hearing is rescheduled.
The council’s Nov. 17 meeting is on the city’s video archive. Promontory is item 9, about an hour and eight minutes in.
The subdivision map and design permit expire Feb. 15, 2027, the staff report says.