A Texas company wants to drill up to six deep wells on a ranch near Clearlake Oaks to find out whether the hot rock underneath could be used to make power. If you live nearby, you can ask about it on Dec. 9.
EGX Energy “recently submitted a major use permit application to Lake County Community Development” for the wells, the East Region Town Hall says in a Nov. 23 post on its website. The town hall is an advisory council appointed by the Board of Supervisors. It represents Clearlake Oaks, Spring Valley and Glenhaven.
The wells would go on Pluth Ranch, at 2060 Sulphur Bank Drive. The post puts the drilling site 0.84 miles north of the city of Clearlake and one mile east of Clear Lake. The application files are on the county’s online permit portal under record PL-26-559, the post says.
The company’s open house is Wednesday, Dec. 9, at the Clearlake Youth Center. Drop in any time from 5:30 to 8 p.m.
What the company says it would do
EGX, based in Katy, Texas, says on its project page that it would drill from a well pad that’s already there. The first well on that pad was drilled in 1981, the page says, and testing found high temperatures underground but not much natural water flow. The well was sealed.
The new wells would go about 1.5 miles down, a company fact sheet says. It puts the site 0.8 miles from the nearest population, behind a ridgeline. The work would take about a year: two months to set up, six months of drilling, four months of testing and two weeks to close.
“Exploration does not mean that a commercial geothermal project will be built,” the project page says. Anything built later would be a separate project with its own review and permits, according to the page.
Neither the page nor the fact sheet says how much water the drilling would use.
What it told the state
In comments filed Sept. 28 with the California Public Utilities Commission, EGX called Pluth Ranch “a planned 100-MW enhanced geothermal system” project with a target of starting commercial operation in 2031. MW stands for megawatts, a measure of how much electricity a plant can make at once. An enhanced system moves water through hot rock so the water picks up heat and comes back to the surface, the company’s page says.
EGX asked the commission to count 100 megawatts from Pluth Ranch as available in 2031 and another 300 by 2034. It said it had secured control of the site and an exclusive agreement to sell power.
The council wants a pause
The East Region Town Hall council voted 3-0 on Oct. 7 to send supervisors a letter. It asks them to pause permits for energy exploration, energy facilities and data centers in its area. The pause would hold until the county adopts a local plan for the east shore area and an update of its general plan that covers energy.
The letter names EGX. It raises concerns about seismic activity and the area’s aging infrastructure, and says three water main failures in the Clearlake Oaks area this year left some residents with no water service. It also says the project is close to the Sulphur Bank Mercury Mine Superfund site, where the letter says major cleanup work is scheduled to begin shortly.
The council’s next meeting is Wednesday, Dec. 2, at 4 p.m. at the Moose Lodge, 15900 Moose Lodge Lane, Clearlake Oaks. Its agenda lists “Status of the October ERTH letter.”